Planning material. It summarizes and links to the authoritative specification and the current measured state — it does not replace either, and it is not current engineering truth.

Identity#

  • Title: IntentGuard — Weekend MVP
  • Visibility: public
  • Repository: w7-mgfcode/intentguard
  • Repository visibility: public
  • Description: Confidence-aware support intent classification with reproducible evaluation, selective prediction and a typed FastAPI inference boundary.

Fields#

FieldType and valuesPurpose
StatusBuilt-in single select: exactly Backlog, Ready, In progress, Review, DoneOnly workflow-state source
PrioritySingle select: MUST, SHOULD, STRETCH, POST-WEEKENDScope boundary and ordering
EstimateNumber, hoursSubtask values are primary; epic and umbrella progress is interpreted as native sub-issue roll-up
Parent issueBuilt-in hierarchyUmbrella-to-epic and epic-to-subtask context; M1 is the native milestone
Sub-issues progressBuilt-in progressEvidence-based roll-up without manual percentage fields

No dates, owners, risk scores, iterations, or automation are added initially.

The Status option list is exact, not a minimum. A new ProjectV2 ships built-in Todo, In Progress, and Done options; the two that the table above does not name were removed so the live field matches this contract. Removing an option clears that value from every item holding it, so an extra option is removed only after a complete, paginated scan proves no item uses it, and an extra option in use stops for a decision instead. The five retained options keep their original option IDs, which is asserted on read-back because resubmitting a name without its ID would delete and recreate the option and silently clear item values.

Views#

MVP Board#

  • Layout: board.
  • Filter: Priority:MUST.
  • Group: Status.
  • Primary sort: Priority in the configured field-option order, which is ascending (MUST, SHOULD, STRETCH, POST-WEEKEND).
  • Secondary sort: Estimate ascending.
  • Scope: all 34 managed M1 issues (W/E/S), filtered to Priority:MUST.
  • Purpose: the smallest actionable strict-MVP view.

Full Backlog#

  • Layout: table.
  • Filter: all real issues, represented in the GitHub UI by no active filter.
  • Required columns: Status, Priority, Parent issue, Estimate, Labels.
  • Primary sort: Priority in the configured field-option order.
  • Secondary sort: Parent issue ascending.
  • Purpose: inspect all 34 created W/E/S issues without mixing in parking-lot prose.

A tertiary Title ascending sort was originally specified here and is Blocked by the platform. GitHub Projects accepts at most two sort criteria per view. This was confirmed in the UI and independently against the GraphQL API: the sort:title-asc filter term does not register as a third sort, and no input type in the schema exposes a sort or grouping input at all (ProjectV2ViewConfigurationInput contains only visibleFieldIds). Two sort criteria are therefore the complete, verifiable requirement for this view.

Umbrella Progress#

  • Layout: table.
  • Filter semantics: label:type:umbrella. A quoted or UI-normalized form is acceptable only when it selects that exact label.
  • Required columns: Status, Priority, Estimate, Sub-issues progress.
  • Sort: Title ascending.
  • Filter result: exactly the three type:umbrella issues W01, W02, and W03.
  • Purpose: compact progress over W01–W03; E/S records are inspected in Full Backlog.

Configuration and verification method#

These three views are configured after the automated Gate D workflow has created and verified the Project, issues, hierarchy, items, fields, and field values.

Sort order must be configured by the user in the GitHub UI. No GraphQL input type expresses a sort, so sorting can be read back but never written by an automated step.

The remaining properties are API-writable and were configured that way: createProjectV2View and updateProjectV2View set name, layout, filter, and visible columns, and setting BOARD_LAYOUT makes GitHub populate verticalGroupByFields with Status on its own. An earlier revision of this document stated that automated view mutation was prohibited because the available interfaces could not express any required grouping or sorting property. That was correct for sorting and incorrect for grouping, layout, filter, and columns.

Any automated view creation must preserve the recorded default view's node ID by renaming it rather than replacing it, because the runbook rejects a changed default-view identity.

Gate D view completion requires all of the following:

  • exactly the three named views above, with no extra managed or unexpected view;
  • authenticated, read-only GitHub UI inspection of each view's Project identity, name, layout, filter, visible fields or columns, grouping, and full sorting order;
  • the user's exact configuration attestation recorded by the execution runbook;
  • one complete, verified execution-state record per view.

Screenshots may supplement the authenticated UI inspection, but cannot replace it and cannot independently authorize verified=true. A pending, blocked, manual-required, incomplete, duplicated, or mismatched view is not completed and prevents Gate D finalization.

Project configuration is a Gate D remote write. Gate D view completion is Implemented. The three views exist on the remote Project with the layouts, filters, columns, grouping, and sort orders recorded above; the user configured every sort order in the GitHub UI and performed the authenticated read-only UI inspection; the exact attestation is recorded; and all three execution-state records are complete and verified. The final read-only verification and execution-state finalization both passed, so Gate D is closed.

The only requirement in this document that is not satisfied is the tertiary Title ascending sort on Full Backlog, which remains Blocked by the two-sort platform cap described above.

Two corrections were made after Gate D finalization. The user set the MVP Board primary sort to the ascending field-option order; the recorded view expectation stores that criterion as the direction string field-option-order, which does not distinguish ascending from descending, so the automated checks could not have caught the earlier descending setting. The two non-manifest Status options were then removed. Neither correction altered any recorded execution-state value: the state stores the Status field ID and the Backlog option ID, both of which are unchanged, so the finalized state remains accurate and was not rewritten. Status is Measured for the live field contents and Implemented for the reconciliation logic.

One property could not be verified. GitHub's GraphQL schema exposes no action or configuration detail for ProjectV2Workflow, so whether the enabled built-in Item added to project workflow referenced the removed Todo option could not be read back. Section 14 already overwrites GitHub's Todo default on every item it populates, and all 34 items read back as Backlog after the removal, so no observed item value depends on it.

Related in repository

Open in full graph →
LINKS_TOLINKS_TO — source: docs/backlog/README.mdREFERENCESREFERENCES — source: docs/backlog/PROJECT_CONFIGURATION.mdREFERENCESREFERENCES — source: docs/backlog/PROJECT_CONFIGURATION.mdREFERENCESREFERENCES — source: docs/backlog/PROJECT_CONFIGURATION.mdREFERENCES — source: docs/backlog/README.mdREFERENCES — source: docs/backlog/README.mdCURRENTdocument: Project configurationLocal GitHub backlogdocument: Local GitHub backlogW01umbrella: W01W02umbrella: W02W03umbrella: W03